Time | Item | Who | Notes |
---|
6min | Status of XSEDE2 ticket queue conversion | Mike | - Still need some queues for the CEE division.
- The 1.6.5 campus bridging queue can be retired as it goes with XCI.
- Victor will check with Chris and Kelly on the last few XSEDE1 queues and what to do with them.
|
2min | Update to the XSEDE Acceptable Use Policy | Victor | - Jim to review and update the AUP and send recommendation draft to Greg to review and bring to XSEDE leadership
|
19min | Cloud services discussion | Victor | Discussion about possibly moving services to the cloud as requested by John/Dave (I obtained some cost info). - Questions that come into play are the compute capacity and storage needed. Most likely a dedicated host resource not on demand.
- Perhaps come up with categorization of which services could easily move to cloud. We need to check.
- Need to also consider the cost of moving the service and the cost savings for application administrator. Also some of the internet costs.
- Need to include the 5 data center contacts to discuss this further as well. Need to know when their upgrade timeframe is.
|
8min | Central Services security monitoring and scanning | Jim | - perfSONAR devices are not Enterprise Services and are not required to be listed in XES-index.
- Regarding perfSONAR getting scanned by the Qualys services, Tim will bring this up on the next call and discuss with adding this scanning to Qualys for the perfSONAR systems.
- Jim asked if there are other services that are not in XES-index that need to be monitored and scanned? The gateway systems are an example. Could look at those systems in the XSEDE Nagios to see what is not in XES.
|
2min | Upcoming IPR information/instructions | Scott | - We will be reporting on Sept and Oct for the first report of XSEDE2.
- Scott will be sending each L3 their template and information on how to complete this.
- There was also a reminder of the email from Leslie Morsek regarding Other Metrics that provides some instructions on how to complete these metrics in the report Appendix.
|
NA | Mgr. coordination | None | Not discussion. Meeting ran over, so this item was tabled. |