XCI Area Metrics

 

Area Metric

Report
Year

Target

RP1

RP2

RP3

RP4

Total

Overall Success

Sub-goal Supported

Average satisfaction rating of XCI services

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

4 of 5/yr

 

 

 

 

 

 

RY1

4 of 5/yr

*

4.8

 4.81

 4.5

4.5 

(star)

Number of new capabilities made
available for production deployment

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

7/yr

 

 

 

 

 

 

RY1

7/yr

 *

 6

(green star)1

Number of capabilities
delivered/ Number planned

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

 

 

 

 

 

 

 

RY1

1/yr

 1

 1

(green star)

Total number of systems that use
one or more CRI provided toolkits

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

900 by the end of RY2

 

 

 

 

 

 

RY1

450/yr

*

512 

51

 31

594

(green star)

Percentage of XSEDE recommended tools
that are adopted by allocated systems
(all Level 1 and Level 2 SPs that are allocated
by XSEDE in whole or in part) where the tools
are appropriate

RY5

       

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

100%/yr

      

RY1

100%/yr

*

100%

100%

100%

100%

(green star)

1 Given a reporting year of 8 months, and a target set for a 12 month year, we consider this metric to have been met for reporting year 1 since we exceeded 2/3 of the goal set originally for 12 months.

'Overall Success' is indicated by a Green (>90% achievement), Yellow (>70% Achievment), Red (< 70% Achievment), or Blue (N/A) star. Some items may have a note indicating special circumstances.

RACD Metrics

 

Area Metric

Report Year

Target

RP1

RP2

RP3

RP4

Total

Overall Success

Sub-goal Supported

Number of capability delivery plans
(CDPs) prepared for prioritized
Use Cases

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

 

 

 

 

 

 

 

RY1

7/yr

*

 9

5

 7

21

(green star)

Number of capability delivery plans
(CDPs) prepared for UREP prioritization

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

12/yr

      

RY1

*

*

*

*

*

*

 

Number of CI integration assistance
engagements

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

6/yr

 

 

 

 

 

 

RY1

6/yr

*

 4

1

0

5

(green star)1

User rating of components delivered
in production
 

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

 

 

 

 

 

 

 

RY1

4 of 5/yr

*

5.0

5.0

 3.5

 3.5

(star)

Operator rating of components
delivered for production deployment

RY5

 

 

 

 

 

 

 

Sustain — Provide reliable, efficient, and secure infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

 

 

 

 

 

 

 

RY1

4 of 5/yr

*

5.0 

4.5

 4.0

 4.3

(green star)

Software/Service Provider rating
of our integration assistance

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

 

 

 

 

 

 

 

RY1

4 of 5/yr

*

5.0 

NA6

4.5 

4.8

(green star)

Average time from support request
to solution

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

<30 days

 

 

 

 

 

 

RY1

<45 days/yr

*

7 days 

16 days 

4 days 

9 days

(green star)

Number of significant fixes and
enhancements to production components

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

16/yr

      

RY1

*

*

*

*

*

*

(blue star)

Number of new components
instrumented and tracked for
usage and ROI analysis

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

4/yr

      

RY1

*

*

*

*

*

*

(blue star)

Average satisfaction rating of RACD
services
 

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

4 of 5/yr

      

RY1

*

*

*

*

*

*

(blue star)

Given a reporting year of 8 months, and a target set for a 12 month year, we consider this metric to have been met for reporting year 1 since we exceeded 2/3 of the goal set originally for 12 months.

'Overall Success' is indicated by a Green (>90% achievement), Yellow (>70% Achievment), Red (< 70% Achievment), or Blue (N/A) star. Some items may have a note indicating special circumstances.

 

XCRI Metrics


 

Area Metric

Report Year

Target

RP1

RP2

RP3

RP4

Total

Overall Success

Sub-goal Supported

Total number of systems that use
one or more CRI provided toolkits

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

700 by the end of RY2

 

 

 

 

 

 

RY1

450/yr

*

512 

51

 31

594

(green star)

User satisfaction with CRI services

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

       

RY2

4 of 5/yr

 

 

 

 

 

 

RY1

4 of 5/yr

*

*

5

NA

5

(green star)

Number of Level 1 total systems that
fully incorporate all of the
recommended tools from the
XSEDE Community Repository

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

       

RY1

5/qtr

*

6

6

6

6

(green star)

Number of repository subscribers
to CRI cluster and laptop toolkits

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

150/yr

 

 

 

 

 

 

RY1

150/yr

*

 91

4

 4

99

(star)

Aggregate number of TeraFLOPS
of cluster systems using
CRI toolkits

RY5

,

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

200/yr

 

 

 

 

 

 

RY1

1,000/length of project

*

532

532

732 

732

(star)

Number of partnership interactions
between XCRI and SPs, national
CI organizations, and campus CI
providers

RY5

 

 

 

 

 

 

 

Advance — Create an open and evolving e-infrastructure

RY4

 

 

 

 

 

 

 

RY3

 

 

 

 

 

 

 

RY2

12/yr

 

 

 

 

 

 

RY1

12/yr

*

52

72

10

22

(green star)

Toolkit updates

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

4/yr

      

RY1

4/yr

*

2

1

6

9

(green star)

New Toolkits released

RY5

      

 

Advance — Create an open and evolving e-infrastructure

RY4

       

RY3

       

RY2

2/yr

      

RY1

2/yr

*

*

1

0

1

(star)


'Overall Success' is indicated by a Green (>90% achievement), Yellow (>70% Achievment), Red (< 70% Achievment), or Blue (N/A) star. Some items may have a note indicating special circumstances.

 

Ongoing Additions to XCRI Metrics:

June 05, 2017: +3 to Number of partnership interactions between XCRI and SPs, national CI organizations, and campus CI providers for meetings w/ Wayne State, Carnegie Institute of Science, and presentation at GPN

 

 

  • No labels