General updates

Next call will be January 10, 2019

Planning and Reporting

  • PY9 planning starts Feb 11
    • Goal will be to start UREP review early Jan
    • Lucille Jarzynka will email UREP members before the break to give them heads up and confirm their participation
  • IPR8 will be due on Feb 21

Project Improvement Ideas

  • We should submit project improvements to be recorded here.
  • We can also submit PIF request anytime here.

Use Case and Capability Delivery Plans

Capability delivery plans

There are now only 20 use cases with no CDP (down from 24 last meeting), and each has an activity in JIRA to produce one, most assigned to an individual.

JP Navarro has finished Community Software Area (CSA) use cases:

  • New CDPs for SPI-07, SPI-08, RC-03, and RC-04 are done
  • Preparing a design document explaining the SP and researcher experiences
  • Will present the use cases, CDPs, and design document to reviewers before we implement

Lee Liming is working on sorting out the current status of CAN-01 (Run a remote job) and the other use cases that rely on it.

New use cases

No new use cases since our last meeting.

Activity Status Updates

Delivered and deployed

Pending deployment


Activity status is now being imported directly thru JIRA – click on attached PDF for status of activities after the meeting.