3/28

All L2 text (including L3 text) due to PMs (recommendation: L3 text due 3/25 to PMs, PMs give text to L2s 3/27)

3/29

All text due in GoogleDocs by PMs, including copy edits

4/1

KPI targets calculated

4/1

Level 1 Priorities (Ron)

4/2

Copy Edit

4/3

John edit content

4/4

Responses to John’s edits

4/5 – 4/8

Clean up PY8 Plan and get it ready for XAB’s review

4/9

PY8 Plan Final Review goes to XAB

4/22 – 4/23

Incorporate XAB comments/suggestions into draft PY8 Plan

5/17

PY8 Plan due (in conjunction with Annual Report)