Includes: | RY6 RP1: May '21 – Jul '21 |
8/5/2021 | All L2 text (including L3 text) due to PMs (recommendation: L3 text due 8/3/21 to PMs/PMs hand-off to L2s, L2 text due 8/5) |
8/6 | All text due in GoogleDocs by PMs; PMs are required to review, revise and ensure the text they receive from their respective L2s is correct (i.e., grammar, context, completeness, formatting, etc.) |
8/9 | KPIs calculated and analyzed |
8/9 | Level 1 Highlights & Summary (Ron) |
8/10 | John & Tim First Pass & PM Copy edit |
8/11 | ER Copy Edit |
8/12 | John & Tim Second Pass |
8/13 | Final day for responses to John/Tim’s comments |
8/16-17 | Noni format report & Leslie Final Review |
8/18 | John final review of Word doc/Submit Report |
8/19/2021 | John submit IPR15 to NSF |