Date
Attendees
Agenda
- IPR status
- follow up on Duo for XSEDE (I sent email to vendor but did not hear back yet)
- Update on central log server XES participants
- Plan for upgrading XES services at our XES infrastructure provider's data centers (NICS, NCSA, PSC, TACC)
- Mgr. Coordination
Discussion items
Time | Item | Who | Notes |
---|---|---|---|
2min | IPR Status | Scott | Scott provided reminder that tomorrow is end of quarter.
|
2min | Status of Duo | Victor | Current license ends 4/29
|
2min | Update on central log server XES participants | Victor | Gary reports we are at 60% XES participation and still adding. |
15min | Plan for upgrading XES services at our XES infrastructure provider's data centers (NICS, NCSA, PSC, TACC) | Victor | Had a first discussion with Ops Mgrs about plan for VM infrastructure to be multiple infrastructure provider data centers than can move VMs between the centers.
|
2min | Mgr Coordination | Security and SysOps collaborative meeting every week immediately after Ops Mgmt meeting XOC back to funding level from before. Mike mentioned things are operating well and he had one person retire and is working on replacement. Offboarding form was submitted and PM&R team executed the process. |